Contact Us Home

August 10, 2003
CONSTRUCTION OF RED HILL CREEK EXPRESSWAY SHOULD NOT PROCEED

Statement of Friends of Red Hill Valley

The City of Hamilton has announced it is preparing court actions against those who are protesting the start of construction of the Red Hill Creek Expressway near Greenhill Avenue. In fact, as explained below, it is the City whose actions are illegal and in violation of the rights of the Haudenosaunee and other First Nations peoples, as well as the rights of nearby residents.

  1. The majority of the proposed construction area is part of King's Forest Park, which has been Hamilton's largest park since its purchase in 1929. The City has not gone through any formal process to sever the proposed construction area from the park, or to re-zone it from its parkland designation. Ironically, the City is threatening to charge the protestors under by-laws that manage the use of parks. Thus the citizens who are trying to protect the park may be charged with obstructing those who have been hired to destroy the park.

  2. Surveys conducted on August 4 have confirmed the presence of a number of species of nesting migratory birds in the area slated for construction. The federal Migratory Birds Convention Act and its regulations forbid the disturbance of migratory birds during their nesting activity. The August 4 survey confirmed that a minimum of four species were maintaining nests, four more species were taking care of young outside the nest, and four additional species were displaying territorial behaviour that may be associated with nesting. The presence of these nesting species requires the delay of construction and the action of the protestors has in fact restrained the City and its contractors from violating federal law.

    The majority of the construction area is also protected under the Niagara Escarpment Planning and Development Act and falls within the Niagara Escarpment World Biosphere Reserve. While the latter designation appears to have little legal strength, this cannot be said of the protection accorded by Ontario law to escarpment lands. Anyone familiar with the mandate of the Niagara Escarpment Commission (NEC) knows that it subjects even very minor land use changes to careful review and regulation. However, this oversight has been circumscribed with respect to the Red Hill Creek Expressway as a result of administrative processes that violate the purposes of the escarpment legislation.

  3. The NEC registered its opposition to the expressway in 1979, the year in which the municipality adopted its roadway plans. In 1984 Commission staff recommended that the NEC deny the municipality's request for a Development Permit. However, the Commission was unable to act because the provincial government established a Consolidated Joint Board hearing process to examine the expressway proposals, and the three-person hearing board used its authority to order the NEC to provide a permit for the project. This was done in 1987 and Hamilton maintains that this 16-year-old permit is all it needs today to build the expressway.

    However, the expressway project has changed dramatically. In 1987 there were no plans for a new cut in the escarpment; today the expressway includes the largest cut ever made by humans in the face of the escarpment - 80 metres wide and 15 metres deep - as well as the blasting of a 400 metre trench. Other changes to the project include the re-location of Red Hill Creek and the creation of 7.6 kilometres of new creek bed (more than a third of it within the Escarpment Plan Area); the erection of a 220 metre viaduct; the construction of three large stormwater ponds; and even a redesign of the Greenhill Avenue interchange that is the focus of the current protest.

    The NEC and its staff have repeatedly stated that these changes require a new Development Permit, but the municipality maintains that its 1987 permit is all Hamilton needs. In June, Friends of Red Hill and the Coalition on the Niagara Escarpment (CONE) jointly asked the NEC to issue a stop work order. This request was tabled by the NEC and further clarification sought on the City's position. At this point no decision has been taken, but since the City believes the NEC has no right to ask for a new permit, the City is proceeding with construction, essentially daring the NEC to try to stop it.

  4. Even if the City is correct in arguing that its 1987 permit is valid, it hasn't yet even bothered to meet the conditions of that permit including the provision of a detailed grading plan and a detailed tree preservation plan which must be approved by the Commission. Instead the City appears to have decided these conditions don't need to be met until sometime after construction begins in the Escarpment Plan Area.

  5. Beyond the NEC permitting issues, the City openly admits that it has not secured other major permits and authorizations needed to build other parts of the expressway. These include authorizations under the federal Fisheries Act to re-locate 7.6 kilometres of Red Hill Creek, and permission to excavate 70,000 tonnes of the toxic Rennie Street Landfill that lies directly in the path of the proposed expressway. This is the same landfill that the City pled guilty in 2000 to allowing to leak PCBs and other chemicals into Red Hill Creek, and received the largest environmental fine in Ontario history. In addition, a federal environmental assessment is now underway to determine if a major oil pipeline can be relocated to accommodate the expressway. We believe for the City to proceed with construction without these permits and in the face of an ongoing environmental assessment is contemptuous of the law.

  6. There is also the matter of notification to the directly affected Greenhill neighbourhood, and provision of an opportunity for consultation and addressing of concerns. While the general features of the expressway have been known for many years, the specific plans for the Greenhill work have only been communicated to the majority of the adjacent homeowners since the beginning of August. Several hundred homes and three schools are within 200 metres of the construction site. Notices were delivered on July 5 to only 23 of the homes, and a flyer was distributed on the last day of school to the children of one of the schools. The remaining homes got a flyer in the mail in early August that promised consultation during June and July! The City has posted its public consultation protocol on its website and it promises that "The consultation will aim to take place a minimum of four weeks in advance of when a final decision is required." Instead, many residents only got their first notification on the day the City tried to start construction.

  7. Finally, and most importantly, any attempt by the City to proceed with work in the Valley must be preceded by an agreement with all the affected Aboriginal peoples. Both the Showstoppers and Friends of Red Hill Valley have been issued a permit by the Haudenosaunee Confederacy to camp in and protect the the Red Hill Valley. The City holds no such permit.

Why is the City of Hamilton rushing into the construction work at Greenhill Avenue? Friends of Red Hill Valley believes that the rush to construction without appropriate permits or consultation is being driven by the upcoming municipal elections. The proponents of the expressway currently control the majority of the votes on City Council, but realize that this may change as a result of the November 10 elections. Instead of waiting for the public to have its say, they are rushing ahead to spend as much money as possible on the project so that they can argue that it's too late to stop the expressway even if the voters reject it. At the same time, pro-expressway councillors may be trying to prove they can deliver the expressway to local land developers and others who provide the bulk of the contributions to their election campaigns.

Friends of Red Hill Valley calls upon the City to withdraw its threats against the protestors at the Greenhill site, and to delay its construction plans until it has obtained the blessings of the First Nations peoples, provided a proper opportunity to the directly affected neighbourhood for meaningful consultation, and obtained all the necessary permits and authorizations related to the expressway project.

For further info: please contact Don McLean (905) 664-8796


© Friends of Red Hill Valley 1991-2005

Sign our Petition!