Contact Us Home

April 10, 2000
COURT RULES THAT FEDERAL ENVIRONMENTAL ASSESSMENT ACT AND FISHERIES LAWS APPLY TO RED HILL EXPRESSWAY

On Friday, April 7, the Federal Court of Canada dealt another blow to the Region of Hamilton-Wentworth's attempts to block a federal environmental assessment of the proposed Red Hill Creek Expressway. The Region has been claiming that the Canadian Environmental Assessment Act (CEAA) doesn't apply to the project, and that it also doesn't require a permit for the project under the federal Fisheries Act. The court ruling rejects both of these claims.

In the ruling, the judge states: "I would not grant leave to assert that authorization is not required for the Expressway Project under subsection 35(2) of the Fisheries Act, or to assert that the need for that authorization did not trigger the application of the CEAA." The judge explains her ruling in the following excerpt from the decision:

"...the Regional Municipality accepted the need for Fisheries Act approval at an earlier stage of the construction project as evidenced by the fact that it sought and in late June 1995 obtained, an authorization pursuant to subsection 35(2) of the Fisheries Act with respect to completion of the Dartnall Road Interchange portion of the Lincoln Alexander Expressway."

"Thereafter, when discussion began between representatives of the Region and the federal authorities in 1996 with respect to the portion of the Expressway now at issue, the Region 'reiterated the fact that the Red Hill Creek Expressway will cause habitat destruction and that a compensation will be developed in consultation with MNR and DFO'. Ultimately, in July of 1998, the Region forwarded its application for authorization under the Fisheries Act. This was done under cover of a letter dated July 24, 1998. The letter stated 'this early submission will facilitate the approval process by providing DFO with the ability to initiate a screening under the Canadian Environmental Assessment Act.' The letter continued, 'the Region acknowledged the requirements of the Canadian Environmental Assessment legislation in developing the impact assessment process that is currently underway'. "

"In short, apparently being of the view that habitat destruction would be caused (so that compensation would be required under the Fisheries Act), having received a response to the Draft Summary Report to the effect that indeed the Project might have harmful impacts on fish and fish habitat, and on the basis of that response, choosing to apply for approval under the Fisheries Act, the applicant [the Region] cannot now assert and rely on the absence of a more formal decision which its own actions, in effect, pre-empted. I accept counsel for the respondents' [federal government] submission that prior to the issuance of the Review Panel's terms of reference, there was no demonstration of any intent to seek judicial review with respect to the requirement of Fisheries Act approval or the application of CEAA."

This decision contradicts the views which the Region and its lawyers have been presenting for some time. Last week, for example, the Region's lawyer stated on television: "There is no need to have another environmental assessment. That went on in 1985, went on for 100 days. The feds didn't participate, they were invited to, declined. Why do they get off trying to run their own process fifteen years later? We think its unacceptable." The Region and its lawyers may find it unacceptable, but the courts clearly think otherwise.

In other parts of Friday's decision, the court ruled against federal government attempts to limit some of the issues in the upcoming court hearing. This overturns an earlier decision that the Region had begun its court challenge too late to address some of the federal actions and decisions that it disagrees with. The court didn't rule on the validity of this argument, only that this would have to be decided at the full court hearing. This means the court case will both last longer and may be more expensive than the environmental assessment. The Region is taking the longer, more expensive federal court route because it is well aware that the project will not pass an independent environmental review.


© Friends of Red Hill Valley 1991-2005

Sign our Petition!