Contact Us Home

January 1998 Newsletter

QUESTION ONE : TRAFFIC NEED

The first question in the PR addresses the traffic need for the expressway. It says the east escarpment crossings are already operating at or near capacity and "traffic generated by an appreciable growth in the area south of the escarpment cannot be reasonably accommodated". It predicts that even the widening of #20 by two lanes would only accommodate 64% of the forecast demand. It bolsters these conclusions with the following quote from a 1994 report of the Ontario Ministry of Transportation (MTO) : "Without some road developments in this area, the existing north/south connections across the escarpment will experience severe congestion in the morning and evening rush hour periods."

This quote is taken from the MTO Technical Report issued as part of David Crombie's 1994 proposal for a four-lane road in the valley. Readers will remember that Crombie concluded that widening Mt. Albion Road from two lanes to four and linking it with the four-lane Woodward Avenue would accommodate all projected traffic growth. Indeed, Mr. Crombie reached this conclusion even though he assumed a population growth rate 25% greater than the region is currently predicting. So how can Crombie's study be used to argue that widening #20 by two lanes is insufficient to meet even current population projections?

The sentence quoted in the PR is from page 2 of the MTO report, in the section titled "Background". This section summarizes views expressed by previous studies. This is normal practice at the beginning of a report, and is done to show that the authors understand what has been said in the past about the issue they are about to re-examine. However, it is not normal practice to quote from the "Background" section and pretend that it represents the conclusions of a report.

Not surprisingly, the real conclusions of the MTO report are found 50 pages further on in the "Conclusions" section of the report. They include that: "A four lane road provides sufficient capacity to meet the long term traffic forecasts, under either a low growth or high growth scenario."

MORE SELECTED QUOTES

The same dishonest use of quotes from the MTO report is found in the answer to the second question addressed in the PR. Once again a sentence is lifted from the "Background" section to claim that alternatives have been examined and "a widened Highway 20 AND a new Mud St. / Fruitland Road expressway would be required to meet the needs of the Region". This quote, as well as two more accompanying it that are also from the "Background" section of the MTO report, again do not represent the conclusions of that report, but merely recount views expressed earlier by the region itself.

It speaks volumes about the expressway when regional government officials resort to such trickery to try to justify the project. The figures they give in the PR for traffic capacity and for future flows shows that they cannot find honest arguments in support of the expressway.

TRAFFIC PROBLEMS?

The PR claims that there already is a traffic problem on #20 and Mt. Albion with "the existing road network operating at or near its current capacity", and that this will get much worse as population grows.

First consider the following statement from a September 1996 regional report: "The Regional Transportation Department has determined that a population of 21,000 will not overload existing escarpment crossing capacity". There are currently about 14,000 people in upper Stoney Creek. So one arm of the Department says road capacity has been reached, while another says that adding 7,000 people will not create a capacity problem. A reality check suggests that there currently is some congestion on #20 between Barton and Queenston, but only very rare problems going up or down the escarpment.

ROAD CAPACITY?

Closer examination of the PR shows that the real cause of its "traffic crisis" is a serious underestimation of road capacity. The PR claims that the current capacity of #20 and Mt. Albion combined is only 2600 vehicles per hour (vph) in the southbound direction, and that widening Highway 20 by another lane in each direction will only increase that capacity to 3400 vph.

Since the PR doesn't tell us the individual capacity for each of Mt. Albion and #20, we have to do a little math. If we widen #20 from two lanes in each direction to three, the PR says the capacity goes up by 800 vph (from 2600 to 3400). That suggests that one lane of #20 provides for 800 vph and therefore the existing #20 provides 1600 vph. Subtracting that from 2600 leaves 1000 for Mt. Albion. This obviously doesn't make a lot of sense since it suggests that the winding Mt. Albion can carry more per lane than #20. We need to do more research.

The Regional Transportation Review published in 1996 tells us the capacity of #20 alone is 2200 vph in each direction. If this is the case, and the PR says 2600 is the total east escarpment capacity, then Mt. Albion's capacity must be only 400 (2600 - 2200). However, 1995 City of Hamilton traffic flow statistics show that Mt. Albion already carries up to 800 vph in one direction.

Using these sources, we can calculate that expanding #20 from two lanes to three would increase its capacity from 2200 to 3300. Add in the 800 already using Mt. Albion, and we get a total capacity of 4100 instead of the 3400 that the PR claims.

HOW MUCH MORE TRAFFIC?

However, the PR says that a capacity of 5300 will be required by 2021. Not surprisingly this figure is also highly questionable. The 1982 Environmental Assessment submitted by the Region to justify a six-lane expressway in Red Hill Valley predicted a peak one way traffic flow of 4500 vph across the east escarpment when population levels reach their maximum in upper Stoney Creek. The 1996 Regional Transportation Review lowered that prediction to 4400 vph.

These traffic projections are based on the Region's predictions of population growth between 1991 and 2021. However, the actual rate of growth in the first five years of that period (1991-1996) was only 57% of what was predicted.

If this trend continues, we could expect that traffic growth would only be 57%. The PR predicts a growth of 2700 vph (from 2600 to 5300) and 57% of that is less than 1550. That would bring total traffic levels to 2600 + 1550 = 4150, or almost exactly the amount available if we simply widen #20. If instead we take 57% of the traffic growth predictions from the Regional Transportation Review of 1800 (2600 to 4400), we get 1025, bringing total levels to only 3625.

In addition, both the 5300 and the 4400 predictions assume that the north-south expressway will be built and that as a consequence a substantial portion of the traffic currently using central escarpment crossings will shift to the east escarpment. The 1996 study thus predicts available capacity on central escarpment accesses of 1600 vph by 2021. If the expressway is not built, this shift will not take place and the flows will obviously be even less.

It is also worthy of note that past traffic predictions of the Regional government have been grossly high. The 1982 Environmental Assessment forecast that combined peak hour flows on #20 plus Mt. Albion would rise from 1850 vph in 1981 to 3900 vph in 2001. We are more than 3/4 of the way through that 20 year period, and the actual increase has been 750 or about 37% of the predicted increase. In fact, the current flows have been stable since 1990.

In summary, the PR grossly under-estimates current roadway capacity, grossly over-estimates the likely growth in traffic over the next quarter of a century, and then uses dishonest quoting to suggest someone else agrees with their conclusions.


QUESTION TWO : ALTERNATIVES?

Question two asks if alternatives have been investigated. As noted above, the answer features more dishonest quoting, in this case inaccurately claiming that MTO rejected widening #20 in 1994. The rest of the PR answer praises the merits of the environmental assessment study done in 1978 which assumed grossly high traffic growth.


QUESTION THREE : MORE TRANSIT?

Question three asks if more transit usage would solve the traffic problems. It answers that hardly anybody wants to use the bus. This is hardly surprising when the transit services are being slashed and the money spent to build nice new expressways to subsidize more car dependency. It says transit use would have to be more than doubled from the current 48 rides per capita per year. It doesn't tell us that the rate has fallen from 75 a decade ago. It is worthy of note that the current Commissioner of Transportation wrote the 1982 environmental assessment of the expressway while he was a consultant to the Region. In it, he argued that building the expressway was cost-effective because it would REDUCE transit use by 4100 passengers a day and result in savings of over $30 million in transit spending. This mentality is now in charge of the HSR!


QUESTION FOUR : POPULATION GROWTH?

Question four focuses on population growth. It has a nice graph showing that the population predictions made in 1982 were too low. It also shows the 1991 to 2021 predictions, but doesn't bother to tell us that they have already been proven to be way too high (see above). One sentence reads: "Of particular importance, the expanded roadway capacity assists in directing growth in accordance with the planned development patterns."

This is simply an admission that the expressway is being built to make the region's growth predictions for upper Stoney Creek come true. This goes to the heart of the expressway issue.

In the 1950s we were told it was needed for 1960s growth. In the 1960s it was going to be necessary for the 1970s. In the 1970s we had to have it for the 1980s, and so on until today, when we still must build it because of predicted growth in the next century. The project is a self-fulfilling one. If we build it, it will create a need for it. If we don't build it, we won't need it.

This section also states that "The development of the Heritage Green Community has been capped at 21,000 because of insufficient roadway capacity." The PR doesn't tell the reader that this "cap" keeps going up. It was "capped" in 1982 at 12,000 as part of the argument that the expressway must be approved. It was "capped" again in 1991 at 15,000 after the Rae government cancelled funding. Both of these "caps" were loudly publicized. Then in 1993 the cap was quietly raised to 16,500. In 1996 it was quietly raised again to 21,000. Meanwhile there are less than 14,000 people in Heritage Green (upper Stoney Creek). The pattern is clear. Every time a subdivision developer's plans threaten to approach the "cap", the cap goes up. In Hamilton-Wentworth, this is called "planning".


QUESTION FIVE : MORE TRUCKS?

Question five asks: "Would not truck traffic increase tremendously, particularly through truck traffic?" Good question, but the PR's answer is even better. It admits that 3,000 trucks a day on the 403 could switch to the new expressways, but then "assumes" that only 25% would actually do so, and declares that "the added traffic volume would represent less than 3% of the total traffic on the roadway".

Why would only 25% of the trucks divert to a new expressway that is 9 km shorter than going around the city and over the skyway? Do 75% of truck drivers like to avoid shortcuts? The PR doesn't venture a guess as to how many cars currently use the 403 or what percentage of their drivers will prefer to take the long way. As for the PR's 3% figure, heavy trucks currently make up 15-20% of 403 and QEW traffic.


QUESTION SIX : CAN WE AFFORD IT?

The next question asks if the region can afford the expressway; but it doesn't bother to answer that toughie. It also asks about downloading; but only responds that "the financial implications associated with the proposed downloading of services from the Province will not be fully understood until agreements are reached between the Region and Province."

Instead of replying to its own questions, this section tries to down-play the costs of the expressway. It features a pie-chart graph claiming that the taxes required for police services are ten times greater than those needed for the expressway. It also states that the east-west expressway will cost the region $85 million and the north-south only $76 million, and this means extra taxes for 25 years of $8 per year for the east-west and $14 per year for the north-south. The PR does not explain why a road that costs $76 million raises taxes nearly twice as much as one that costs $85 million. However, we are assured that "the costs represent only 0.5% of the total average property tax bill (regional, municipal and education taxes)."

The $22 a year (8 + 14) for 25 years in taxes (total $550) is a gross understatement. What the PR appears to have done is forgotten that the money is being borrowed. It lists the regional share of the expressway construction cost as $161 million (76 + 85). When borrowed over 25 years that becomes $373 million. The 1997 rule of thumb is that each $1 million in regional expenditures costs the average homeowner $3.50. The cost of the expressway for each average taxpayer should therefore be $1305.50 (3.50 x 373).

The region hopes to collect $55 million for the expressway from development charges on new homes over the next 25 years, so the $373 million may be reduced to $318 million or $1113 for each average taxpayer.

However, there is another factor that needs to be considered. Up until last year, it cost the average taxpayer only $3.29 for each $1 million in regional expenditure. This year, the cost rose to $3.50 because of provincial cutbacks. In effect, the regional taxpayer pays a larger share of the expenditures today than they did a year ago. This trend is continuing with a vengeance. Figures recently released by the region on the provincial downloading appear to assume that the rule of thumb is now over $4.00 per million. That could raise the average homeowner's bill for the expressways to nearly $1500.

And this is just the cost of building the expressways. It doesn't include the operating and maintenance costs which the Regional Chairman says will equal the construction cost in the first 20 years. Our math says that is over $8 million a year (total regional cost of $161 million divided by 20). Plus the environmental costs, and the monies paid from provincial taxes.


QUESTION SEVEN : SAVING THE ENVIRONMENT

Question seven asks if the cuts in cost have been at the expense of the environment. (Note there is no question about whether the project itself is at the expense of the environment). This question arose because $41 million disappeared from the expressway bill last February . Those "savings" have never been explained. Indeed, the PR doesn't even mention the $41 million figure. It does tell us that the "savings" include the "deferral of the construction of Phase 2 of the Highway 403 and Mud Street interchanges". If "deferral" still means the same in PR language as it does in ours, it would be nice to know how much extra cost to expect when those "deferrals" end.

The PR answer is decorated with a picture of the "wetland" created by the Region in the middle of the Dartnall Road interchange as "evidence of the Region's commitment to the natural environment". The exact value of wildlife habitat located in the middle of an expressway interchange is not addressed (advice to wildlife: don't try crossing the road). However, we have learned that the runoff from the expressway of PAHs and heavy metals will require that this "natural environment" be regularly dredged and the material taken to a toxic waste dump.


QUESTION EIGHT : MOST EXPENSIVE ROAD?

The next question and answer provides more fun with figures. The question is "Isn't this the most expensive roadway built in Canada?". Now where did the PR get that question?

Its answer is even better: "While comparisons to other roadways can be misleading because no two roadways are alike over a fixed distance, the average design and construction costs of both the Expressway and Highway 407 in Toronto are approximately $15 million per kilometre." The word to note is "approximately".

The per kilometre cost of the 407 is $13.5 million. The PR gives the total cost of the east-west and north-south as $367 million. Since they total 19 kilometres, our math calculates "approximately" a cost per kilometre of $19.3 million. However, including the east-west in our calculations is perhaps unfair because the PR is devoted to a defence of the north-south expressway.

The latter is 7.5 kilometres in length. Its total cost is given as $199 million. That gives a cost of "approximately" $26.3 million. To paraphrase a quote: "There are lies, damned lies, and regional government statistics".


QUESTION NINE : THE COST OF PARKLAND?

The ninth question asks why the Region is paying far more to private landowners than to the City for the lands to be used for the expressway. The answer: "All land acquisitions are based on fair market value" and "the valley lands are not suitable for development and therefore cost less". Of course the PR doesn't reveal that some private lands have fetched $300,000 an acre, while the valley lands owned by the City are going for $5,000 an acre. Nor does it reveal that replacing the valley lands with new parkland anywhere in the lower city will cost at least $150,000 per acre. If the City merely asked for 'replacement value' for the lands, the cost of the expressway would rise by at least $20 million.


QUESTION TEN : PROPERTY VALUES?

The tenth question asks "Will the expressway significantly affect property values in adjacent neighbour-hoods?" The answer? "Evidence to support this claim has not been demonstrated in the research". Apparently that's why local house-builders advertise so much about the attractions of "ravine lots". Perhaps the Region missed a 1996 Environment Canada study that found residential properties located 30 feet from a greenbelt "have an excess value of $3,252 over that of a property located 500 feet from the greenbelt".


AND THE "PR" GOES ON

The last three questions are devoted to reassuring the public that the Region will "try "to reduce negative impacts of the expressway and will keep the public "informed through progress reports and public information centres".

We can hardly wait.


© Friends of Red Hill Valley 1991-2005

Sign our Petition!