Contact Us Home

March 2005 Newsletter

UPDATE: Rennie Street Landfill Excavation

After spending almost $12 million to clean up the site, the city of Hamilton is now spending over $15 million to excavate approximately 70,000 tonnes of waste from the old Rennie Street Landfill. The waste must be removed from the southern portion of the site in order to allow for construction of the Red Hill Creek Expressway.

Work has started at the site with the city’s contractors currently completing the installation of a retaining wall to hold back the remainder of the landfill as the southern portion is excavated. As of the beginning of March, the retaining wall work is yet to be completed. Once done, the fullblown excavation of waste will begin.

The Rennie Landfill Community Liaison Committee continues to raise concerns about the excavation work. From the start, the CLC has indicated that it does not support the city’s decision to disrupt the Rennie landfill in any way. Now that the site has been contained, to disrupt it through excavation poses risks the CLC believes should not be taken.

The city has indicated to the CLC that it is doing the excavation work in the winter to minimize odour and dust impacts on surrounding residents. But the work is far behind the original schedule, which had the retaining wall completion date set for late November of last year with fullblown excavation starting immediately after. As of March 2, the new mid-June completion date appears quite optimistic. Even if the remainder of the City’s schedule is accurate, the excavation will likely take until the middle of July.

The main reason for the delay in starting work at the site resulted from challenges faced by Dufferin, the main contractor on the project, in securing an appropriate subcontractor to do the landfill excavation work. At the end of the day, Dufferin announced it would to the work itself, although the company’s experience with the excavation of hazardous landfills appears to be extremely limited.

To make matters worse, the final disposal point for any PCB-contaminated waste that is excavated from Rennie is Bennett Environmental’s St. Ambroise, Quebec facility. But in September of last year, Quebec’s Minister of the Environment, after learning that dioxin/ furan levels in the soil surrounding the St. Ambroise facility, were increasing, ordered the company to take measures to curb emissions from their facility stack. While the company has indicated to Dufferin that it’s ‘business as usual’ at this facility, the Rennie CLC has raised concerns with both the Ontario Minister of the Environment and the Quebec Minister of the Environment, asking for assurances and an update regarding this facility. The CLC does not want to see a contamination problem from Hamilton create a new contamination problem in a community somewhere else. As of early March, no response has been received from either Minister.

The Rennie CLC also had the opportunity in late October of last year to raise many of its concerns directly with Ontario’s Minister of the Environment Leona Dombrowsky. Hamilton East MPP Andrea Horwath also attended that meeting, offering her support and sharing the concerns raised by CLC members. Following on that meeting, the CLC sent the Minister a detailed letter with the ultimate request that the province revisit the Rennie issue as an appropriate provinciallevel assessment of the excavation plans for the site was never undertaken. MPP Horwath also sent a letter. The Minister did not reply to the CLC’s letter nor did she reply to MPP Horwath’s letter. Both parties sent follow-up letters to the Minister in early February of this year. And, again, both parties are awaiting a response from the Minister.

Copies of both of the letters prepared by the CLC and sent to the Minister are posted below. These letters provide more details regarding the concerns of the CLC.

Note: The complete March 2, 2005 CATCH Article Increased Health Risk from Toxic Landfill is available at: www.environmenthamilton.org/CATCH


© Friends of Red Hill Valley 1991-2005

Sign our Petition!