Contact Us Home

September 2001 Newsletter

The City's Plan to "Fix" the Creek

The City is attempting to justify its valley tree cutting plans as an environmentally positive action. They are claiming that the majority of the proposed cutting (1800 trees) is necessary in order to reduce erosion in Red Hill Creek by re-routing the creek bed. What are the facts?

  1. The City has refused to release its plans for re-location of the creek, either to the public or the or to the appropriate regulatory agencies.

  2. The partial map released in March 2000 shows that the entire creek is to be re-located between the Bruce Trail bridge and the TH&B railway.

  3. The most severe erosion problems in the creek have all been caused by previous human attempts to control or re-route the creek.

  4. The other major cause of erosion in the creek has been development in the watershed which has replaced natural areas with pavement, buildings and other impervious surfaces.

  5. It is well known that trees and other natural vegetation prevent erosion problems.

  6. There are significant problems in Red Hill Creek which the City has left to fester unattended for many years

(1) The City has refused to release its plans for re-location of the creek, either to the public or the or to the appropriate regulatory agencies.

We know in general that the City plans to re-locate seven kilometres of the creek as part of its expressway plans. This plan was one of the main reasons for the initiation of the federal environmental assessment in June 1998. The City applied for a Fisheries Permit in July 1998 but did not submit their detailed plans or their background studies related to the creek re-location. A federal document titled "Re: Red Hill Creek" and dated August 13, 1998 noted:

"On July 25, DFO received an incomplete application for work affecting fish habitat. In many places where detailed information was requested on the application form, the proponent specified that 'information not available at this time'. Although the documents include basic information about the 're-alignment of the creek itself (the essential part of the plan)', the data provided is definitely insufficient to allow determination of impact. DFO is examining the entire application along with the 'draft' documents and will officially request additional information in the near future."

A second federal document, dated March 18, 1999 contains the following statement:

"Between August 1998 and February 1999, Fisheries and Oceans requested additional information from the proponent on four occasions. The Region has recently stated that it is not yet in a position to provide the requested information, nor to provide an anticipated timeframe for the submission of the information."

This failure to present detailed plans for the stream re-location made it impossible for the federal government to complete the screening assessment. Instead, the decision was made to move to a Panel Review. The letter from the Fisheries Minister asking for this Panel Review stated,

"that the Regional Municipality of Hamilton-Wentworth has been less than forthcoming with information necessary, at least from a fish habitat standpoint, to complete the screening."

In March 2000, the City attempted to expropriate a private property in the valley. At the expropriation hearing, they presented a map of the proposed relocation of the creek between the Bruce Trail bridge and the TH&B railway. However, they refused to provide any information on how they arrived at this plan or why it was a good idea. As a result, the hearing officer refused to allow the expropriation to proceed.

(2) The partial map released in March 2000 shows that the entire creek is to be re-located between the Bruce Trail bridge and the TH&B railway.

Starting from the Bruce Trail bridge, the new creek goes along the foot of the escarpment and emerges in the middle of the fairway for hole 11 of the King's Forest Golf Course. This first section is currently mature hardwood forest. This is where the City estimates that 1800 trees will be cut down. After crossing the fairway of the 11th hole, the new creek crosses portions of the 2nd, 3rd, 4th, 6th and 13th holes. It then crosses the paved valley trail four times upstream of Rosedale Arena. Below Rosedale Arena it passes directly through all four baseball diamonds and goes along the base of the west wall of the valley just below Charlotte and Dundonald Streets. The entire area north of the extension of Greenhill Avenue is designated as a "stormwater detention area". At no point does the new creek follow the bed of the existing creek.

The 400 metre portion of the creek between the Bruce Trail bridge and the golf course is stable channel that has apparently not moved for hundreds of years. Erosion problems are occurring in the golf course portion of the stream, largely as a result of attempts made by the city to channelize the creek using gabion baskets and concrete structures.

(3) The most severe erosion problems in the creek have all been caused by previous human attempts to control or re-route the creek. The most dramatic examples have been caused by the installation of concrete channels at King Street and Queenston Road.

This is obvious to the casual observer, but it is also the view of consultants hired by the City in 1997 to evaluate erosion problems in the creek. Here are some of the comments from that 1997 report:

"This study concluded that all of the erosion control structures in this reach [golf course] have either generated enhanced downstream or upstream rates erosion rates of the bed and/or bank of the creek. Also, all of the erosion control structures in this reach have either failed to mitigate stream bank erosion or are beginning to be undermined."

"In the cases of the concrete channel at Queenston Road and the gabion baskets in the golf course area, both of these areas have transferred higher stream energy downstream from reduced roughness of the bed and banks of the channel and modified the velocity distribution of the stream. The results are enhanced erosion downstream with rates of bank erosion exceeding one metre per year in the case of downstream of Queenston Road. Other than these few localized areas, erosion to these reaches has remained relatively low at 'typical' erosion rates of centimetres per year."

"In more recent times (last 20 years) much of the channel migration has been initiated from channel re-alignment or erosion control structures which have failed."


(4) The other major cause of erosion in the creek has been development in the watershed, which has replaced natural areas with pavement, buildings and other impervious surfaces. This causes much higher flows during rainstorms, significantly increasing erosion in the creek.

This is the source of erosion problems in nearly all urban creeks. Most of the development in the upper and lower watersheds of Red Hill Creek has occurred in the last 50 years. Many municipalities require new subdivisions to build stormwater ponds and other facilities to prevent increases in runoff. Hamilton has been very backward in this area. The study quoted above stated:

"The earliest set of air photos used are believed to be from 1948... the significant observations are as follows: generally the system appeared to be in balance as there were not signs of excessive sedimentation or erosion."

"Over the period of record [1978 on] ... the frequency of bankfull discharges have increased from approximately twice per year to five to six times per year."

"This is a consequence to changes in the overland flow as discussed in the hydrology report by Phillips P+E (1997) where the percentage of impervious area has increased from approximately 50% to 90% for the entire watershed over the same time period."

(5) It is well known that trees and other natural vegetation prevent erosion problems.

This is also confirmed in the 1997 City study. It noted the following conclusions from a 1995 City study:

"The results of this study concluded that for the Red Hill Creek reach studied, the present state of the stream is relatively stable but is strongly dependent upon vegetative control of tree root masses along the stream banks. Removal of the vegetation in this reach would dramatically increase the rates of stream channel erosion with the current meander pattern."

The 1997 study found that erosion rates below Queenston Road and beyond the influence of the concrete channel were relatively low. It noted:

"The governing reason for the low erosion rates under the changing watershed hydrology from urbanization is by vegetative control of the banks. It has therefore been identified that under the current stream morphology configuration (i.e. meander pattern) the vegetation in these areas must persist along the banks of the stream to maintain the stability of the channel."

"The most contrasting velocities are for the vegetated and non-vegetated threshold velocities for stream bank erosion in the clay materials. Under non-vegetated or sparsely vegetated conditions (short grasses), significant stream bank erosion can be initiated in velocities ranging between 0.5 - 0.75 m/s [metres per second] which is well below bankfull velocity and would likely relate to a discharge frequency between 15-20 times per year. Conversely, densely vegetated banks with tree masses can withstand velocities much higher than bankfull discharge (2.5 - 3.0 m/s) before predominant erosion would likely ensue. This implies that as long as Red Hill Creek maintains a sufficient flood plan to maintain a velocity distribution to that of bankfull discharge under high flows, a densely vegetated stream channel should be maintained or enhanced to mitigate bank erosion for this particular type of geology."

"Long-term stability of the creeks are strongly dependent upon large woody debris as vegetative control against stream bank erosion."

(6) There are significant problems in Red Hill Creek, which the City has left to fester unattended for many years.

Indeed, virtually all the problems in the creek are caused by actions or inactions by the City.

In the 1950s, the City began flushing its combined sewer system into the creek. Combined sewer overflows (which carry a combination of rainwater and raw sewage) now exist at Greenhill, Lawrence, Queenston and Melvin. A plan to prevent these overflows was adopted by all levels of government in 1992 as part of the Hamilton Harbour Remedial Action Plan. The City has not implemented the plan. Instead they have tied the implementation to the expressway, promising to fix the sewage problems only when they construct the roadway.

In the 1960s, the City installed a trunk sewer line down the middle of the valley. Parts of the creek were re-routed to accommodate this sewer line, and concrete pads were put into the creek bed wherever the line crosses the creek. The concrete pads have all caused severe erosion. There are also odour problems associated with this sewer line.

In the 1970s, the City built King's Forest Golf Course, over the objections of the Hamilton Region Conservation Authority. Concrete and other structures were put in place to keep the creek from affecting the golf course. All of the bridges have since been washed out at least once, with the most recent collapse taking place in 1999. Remedial work done in this area in 2000 has already begun to erode.

In the late 1980s, the City installed a Combined Sewer Overflow tank at Greenhill Avenue. Immediately, local residents were assaulted with foul odours. Despite repeated protests, the odour situation has never been corrected. In addition, massive overflows of combined sewage and stormwater continue to occur about 25 times a year. A continuous flow of raw sewage has occurred from this pipe for several years resulting in extremely high e-coli bacterial counts in a pond immediately downstream of the pipe. The overflow pipe is in the centre of eight heavily-used baseball diamonds whose users are frequently subjected to extreme odours.

The City's "solution" to this problem was first to ignore it, then to install a chain link fence and warning signs around the pipe and overflow area (the fence is now gone), and then to occasionally pump out the contaminated pond (this no longer occurs). Several months ago City officials claimed to have found the source of the leak but nothing has been done to fix it. The City is now proposing to build a second retention tank to supplement the existing one. Citizen demands that the City promise to eliminate the odour problem have been rejected.

In 1990-91, the City installed a 220 metre concrete channel at Queenston Road, and a smaller one at King Street as part of the preparations for the expressway. It quickly became apparent that the channels were blocking the spawning run of Chinook Salmon and other fish in the creek. All agencies, including the City, have admitted there is a major problem here since 1993. The City says it will fix the problem when it builds the expressway. Each year, citizens rescue the migrating salmon and carry them past the obstructions. As noted above, both these channels have created enormous erosion problems immediately downstream.

In the 1990s, citizen investigations conducted under the direction of Dr. George Sorger of McMaster repeatedly found fecal contamination in a string of pipes flowing into the creek. In one case, the Ministry of the Environment successfully prosecuted a City employee. However, all of the pipes remain contaminated. The City has taken no action to clean them up.

CONCLUSION

The City's claim that they are trying to "fix" the creek is highly suspect, but impossible to fully evaluate until all the relevant studies and documents are made public. The claim made on August 21 that the tree cutting south of the golf course would be necessary even if the expressway were not constructed is also highly suspect, especially since the City's only obvious interest in the valley is as an expressway corridor. The obvious solution is for the City to publicly release all its plans and ASK the federal government to conduct a full environmental assessment of these plans and the accompanying expressway project. Of course, the opposite is the current course of the City, which has spent over $4 million trying to prevent a federal environmental assessment.

Finally, we should put the "plans to fix the creek" in context. City staff stated earlier this year that we are $2 billion behind in maintenance of the water and sewer system. It will cost at least another $300 million to complete the 1992 plans to stop raw sewage flows to the creeks and harbour. We were told three years ago that the western interceptor trunk sewer line handling all of lower Hamilton and Dundas' sewage is in bad shape and needs to be replaced. Even the plans for stopping raw sewage flows into Red Hill Creek are on hold because of a lack of money. More than $60 million in City capital projects was dropped from this year's budget because of a lack of funds. One of these was the twinning of the drop shaft at Greenhill that is supposed to end more than ten years of foul odours in the Rosedale neighbourhood. This list could go on and on.

A significant part of the problems facing the City stem from the fact that both Council and staff seem incapable of setting reasonable spending priorities. In this case, scarce funds and staff time that should have been directed at fixing our water and sewer systems have been redirected in an ill conceived scheme to reduce erosion by clearcutting.


© Friends of Red Hill Valley 1991-2005

Sign our Petition!