Contact Us Home
September 2000 Newsletter

Increasingly Desperate Attempts to Stop Assessment

The supporters of the Red Hill Creek Expressway seem to be growing increasingly desperate in their attempts to stop the independent environmental assessment of the project by a federal Panel. Last summer they were accusing Sheila Copps of interfering in the process, although they were never able to produce any evidence for this accusation. By April of this year, they were DEMANDING that she interfere, even though this is obviously inappropriate and likely illegal.

Hamilton West MP Stan Keyes, along with Regional Chairman Terry Cooke were reported to be demanding that Sheila Copps "press cabinet colleague Environment Minister David Anderson to limit the review to questions of exclusive federal jurisdiction." On April 18, Mr. Keyes addressed the Canadian Club of Hamilton and attacked Copps "for not taking a stand on the need to limit the scope of a federal environmental review of the controversial Red Hill Creek Expressway project". This pressure from Keyes and Cooke and other pro-expressway forces to interfere in the Panel Review essentially amounts to trying to get the law broken. The Panel Review of the expressway is a quasi-judicial process that must operate at arms length from the federal government.

The demands that the law be broken closely followed a Federal court decision in early April which rejected the major claims being made by the Region in its court case. The Region is arguing that the Canadian Environmental Assessment Act (CEAA) doesn't apply to the expressway, and that it also doesn't require a permit for the project under the federal Fisheries Act. The court ruling rejects both of these claims.

In the ruling, the judge stated: "I would not grant leave to assert that authorization is not required for the Expressway Project under subsection 35(2) of the Fisheries Act, or to assert that the need for that authorization did not trigger the application of the CEAA." The judge explained her ruling in the following excerpt from the decision:

"...the Regional Municipality accepted the need for Fisheries Act approval at an earlier stage of the construction project as evidenced by the fact that it sought and in late June 1995 obtained, an authorization pursuant to subsection 35(2) of the Fisheries Act with respect to completion of the Dartnall Road Interchange portion of the Lincoln Alexander Expressway."

"Thereafter, when discussion began between representatives of the Region and the federal authorities in 1996 with respect to the portion of the Expressway now at issue, the Region 'reiterated the fact that the Red Hill Creek Expressway will cause habitat destruction and that a compensation will be developed in consultation with MNR and DFO'. Ultimately, in July of 1998, the Region forwarded its application for authorization under the Fisheries Act. This was done under cover of a letter dated July 24, 1998. The letter stated 'this early submission will facilitate the approval process by providing DFO with the ability to initiate a screening under the Canadian Environmental Assessment Act.' The letter continued, 'the Region acknowledged the requirements of the Canadian Environmental Assessment legislation in developing the impact assessment process that is currently underway'."

"In short, apparently being of the view that habitat destruction would be caused (so that compensation would be required under the Fisheries Act), having received a response to the Draft Summary Report to the effect that indeed the Project might have harmful impacts on fish and fish habitat, and on the basis of that response, choosing to apply for approval under the Fisheries Act, the applicant [the Region] cannot now assert and rely on the absence of a more formal decision which its own actions, in effect, pre-empted. I accept counsel for the respondents' [federal government] submission that prior to the issuance of the Review Panel's terms of reference, there was no demonstration of any intent to seek judicial review with respect to the requirement of Fisheries Act approval or the application of CEAA."

This decision contradicts the views which the Region and its lawyers have been presenting for some time. For example, the Region's lawyer stated on television: "There is no need to have another environmental assessment. That went on in 1985, went on for 100 days. The feds didn't participate, they were invited to, declined. Why do they get off trying to run their own process fifteen years later? We think its unacceptable." The Region and its lawyers may find it unacceptable, but the courts clearly think otherwise.

In other parts of the decision, the court ruled against federal government attempts to limit some of the issues in the upcoming court hearing. This overturns an earlier decision that the Region had begun its court challenge too late to address some of the federal actions and decisions that it disagrees with. The court didn't rule on the validity of this argument, only that this would have to be decided at the full court hearing. This means the court case will both last longer and may be more expensive than the environmental assessment. The Region is taking the longer, more expensive federal court route because it is well aware that the project will not pass an independent environmental review.

More recently, a new regional tactic has emerged which alleges that Environment Canada staff are biased against the expressway because some of them personally support environmental protection. Part of the accusation is that Friends of Red Hill has infiltrated Environment Canada! This was apparently raised by Mr. Estrin at the August 9 regional council meeting. The Stoney Creek News reported the story as follows:

"Referring to email documents the region obtained under Freedom of Information access, Mr. Estrin said they 'prove' Environment Canada officials in its Burlington office have 'manipulated the process' and government officials have been 'unfair and biased' in judging the Region's claims that the Red Hill Creek Expressway won't detrimentally affect the environment. The documents, he said, point to a 'friends network' that currently exists at the Canada Centre for Inland Waters and in Environment Canada."

These latest accusations suggest an increasing desperation on the part of the Region and its lawyers, who are apparently willing to stoop to almost anything. It's certainly a novel argument for a government to claim that it is the victim of a grand conspiracy of the citizens, especially one lead by a group that was dismissed a couple of years ago as "a handful of zealots". More curious however, is the apparent thesis behind these accusations.

Environment Canada's "crime" was to conclude that the expressway was likely to cause significant adverse environmental effects that couldn't be mitigated. This was hardly an extraordinary view. The Region itself admitted in its 1998 Draft Summary Report that "High-level impacts will occur throughout the entire Red Hill Creek valley system including the re-entrant section into the Niagara Escarpment" and that "High-level impacts cannot be mitigated due to the magnitude of their effects in the landscape and the lack of opportunities to replace similar ecological functions elsewhere in the Watershed" (p.49) There were nearly identical findings for the Red Hill /Van Wagner's Marsh areas. So what is the point of trying to claim that Environment Canada was biased when they simply came to the same conclusions as the Region's scientists?

One is forced to the conclusion that the "bias" campaign is primarily intended to whip up more hysteria against Friends and others who have raised concerns about the expressway project.


© Friends of Red Hill Valley 1991-2005

Sign our Petition!